Tarra Trail Stage Two

Overview:

Commence Date: 01/08/2019
Where:  Yarram-Port Albert Road, Port Albert
Budget: $500,000

Contact:

Name: Wellington Shire Council
Phone: 1300 366 244
Email: enquiries@wellington.vic.gov.au

Details:

Tarra-Trail

 

Project Overview

This project involves the construction of a 6km long 2.5m wide shared path connecting Alberton and Port Albert along the Yarram-Port Albert Road. Once constructed the new shared path will connect with the previously constructed pathway to Yarram and facilitate easy movement between Yarram and Port Albert.

 

Scope of Works

  • Native vegetation protection works
  • Earthworks and drainage works
  • Gravel and concrete path construction
  • Road crossing installation

 

Timelines

August 2019 Construction commences
April 2020 Estimated project completion

 

Current Status

Tender stage

 

Tarra-Trail-Plan