Sale CBD Infrastructure Renewal Program

Overview:

Commence Date:
Where:  , Sale
Budget: $3,045,000

Contact:

Name: Built Environment
Phone: 1300 366 244
Email: enquiries@wellington.vic.gov.au

Details:

Foster Street

Works have been awarded to Cranes Asphalting P/L

New kerb and channel, and footpath have been installed on the South side of Foster Street.

The contractor is currently undertaking works on the North side of Foster street.

Works are anticipated to be complete by June 2019.

 

York Street Streetscape

Streetscape portion of the works is currently in the design and consultation stage.

AusNet services will be undertaking powerline works on a section of the road in 2019.

Gippsland Water has completed works on the water main relocation.